Response Plan: Section 2. Notification Procedures

Section 2 would include the following:

(a)  Notification requirements that apply in each area of operation of pipelines covered by the plan, including applicable State or local requirements;

(b)  A checklist of notifications the operator or qualified individual is required to make under the response plan, listed in the order of priority;

(c)  Names of persons (individuals or organizations) to be notified of a discharge, indicating whether notification is to be performed by operating personnel or other personnel;

(d)  Procedures for notifying qualified individuals;

(e)  The primary and secondary communication methods by which notifications can be made; and,

(f)  The information to be provided in the initial and each follow-up notification, including the following:

(1)  Name of pipeline;

(2)  Time of discharge;

(3)  Location of discharge;

(4)  Name of oil involved;

(5)  Reason for discharge (e.g., material failure, excavation damage, corrosion);

(6)  Estimated volume of oil discharged;

(7)  Weather conditions on scene; and,

(8)  Actions taken or planned by persons on scene.