(a) General. Except as provided in paragraphs (b) and (c) of this section, each new pipeline and each main line section of a pipeline where the line pipe , valve, fitting or other line component is replaced must be designed and constructed to accommodate the passage of instrumented internal inspection devices in accordance with NACE SP0102 (incorporated by reference, see § 195.3).
(b) Exceptions. This section does not apply to:
(1) Manifolds;
(2) Station piping such as at pump stations, meter stations, or pressure reducing stations;
(3) Piping associated with tank farms and other storage facilities;
(4) Cross-overs;
(5) Pipe for which an instrumented internal inspection device is not commercially available; and
(6) Offshore pipelines, other than lines 10 inches (254 millimeters) or greater in nominal diameter, that transport liquids to onshore facilities.
(c) Impracticability. An operator may file a petition under § 190.9 for a finding that the requirements in paragraph (a) of this section should not be applied to a pipeline for reasons of impracticability.
(d) Emergencies. An operator need not comply with paragraph (a) of this section in constructing a new or replacement segment of a pipeline in an emergency. Within 30 days after discovering the emergency, the operator must file a petition under § 190.9 for a finding that requiring the design and construction of the new or replacement pipeline segment to accommodate passage of instrumented internal inspection devices would be impracticable as a result of the emergency. If PHMSA denies the petition, within 1 year after the date of the notice of the denial, the operator must modify the new or replacement pipeline segment to allow passage of instrumented internal inspection devices.
[Amdt. 195-102, 84 FR 52294, Oct. 1, 2019]